Munich City Drainage - Bohrtec
Client | City of Munich Munich City Drainage Friedenstr. 40 81671 Munich |
Contractor | Gwd-system GmbH Karlstraße 13a 66557 Illingen |
Location and location of the construction site | Sewage treatment plant Gut Großlappen, Fresinger Landstraße 187, 80939 Munich |
Brief description of the building task | Production of two horizontal filter strings, each 24m long. Holes were made with 324mm steel casing and lined with stainless steel winding wire filters DN250. Drilling rig BM400 LS |
Client's service description | Production of horizontal filters |
Special suggestions from the contractor | none |
Description of the soil in the soil survey | Gravel/Sand |
Ground encountered | Gravel/Sand |
Tunnelling depths | -6.40m below GOK |
Accuracy vertically and horizontally | 0,01 |
Execution time and rate of advance | Execution period including all ancillary work 6 weeks, 6.00 m/h propulsion |
Tunnelling length | 24m |
Particularities | Core drilling through 90cm bored pile wall (concrete), preventive sealing against groundwater by installing preventers and production of sealing blocks by injection behind the bored pile wall with Sika Inject 102 (Sika Group) |