Switzerland - St. Gallen
| Participants | |
|---|---|
| Bauherr | Stadtwerke St. Gallen, Schweiz | 
| Contractor | Subunternehmer Huber Leitungsbau | 
| Ort der Baustelle | St. Gallen, St. Leonhard Straße | 
| Tender | |
| Beschreibung | Two steel pipe jackings OD 609 mm for crossing under 3 streets for the installation of community heating pipes | 
| Ausgeschriebene Leistungen | Guided steel pipe jacking, distance 59 m to cross under 3 streets with 7 lanes, soil conditions refill material, clay, bricks, old foundations etc. | 
| Alternative Methodes des Auftragnehmers | Guided steel pipe jacking with down-the-hole hammer | 
| Depth of Coverage | 2 m | 
| Accuracy | vertically ± 5 cm; horizontally ± 15 cm | 
| Time for Job or Production Rate | 3 weeks including job site setup and changing the positions of the jacking frame for the second drive | 
| Driving Length | 59 m | 
| Any other Specifics | Obstacles in 15 m distance from the launch shaft, 25 cm under the bottom and above the top of the steel pipe | 
| Ground conditions | |
| Described Ground in the Ground Report | Refill material, clay, bricks, old foundations etc. | 
| Encountered Soils | Refill material, clay, bricks, parts of old foundations etc. | 
							